When building and payments drift apart
Ask in writing for an explanation and a revised timetable. Check with your lawyer what the contract says about delay before you withhold a payment. Our guide to construction delays sets out the next steps.
In short
If you pay for a Georgian new build in instalments from abroad, tie each payment to a stage that can be verified and have that stage evidenced before you pay. Dated photos and videos from the developer, the permit documents and visits by an independent engineer or a local property manager serve this purpose. If construction and payments drift apart, ask your lawyer what the contract allows before you withhold anything.
The four stepsOur guide to payment plans explains how they are structured. This one is about policing them while the building goes up.
Developer payment plansProcess
Monitoring starts before you sign. What the contract does not make verifiable is hard to verify later.
Link each payment to a stage you can see: the frame up to a given floor, the roof, the facade, windows, service connections. A date on its own says nothing about how far the building has got.
Have the contract require dated photos and videos before each instalment falls due, showing your floor and the whole building. Ask for shots with recognisable landmarks.
See the building permit at the outset, and with any major change, such as extra floors, ask for the approved version. The permit names the authority that issued it. The final step is the commissioning of the building.
Before major instalments, hire an independent structural engineer or a local property manager to inspect and document progress in writing. Choose someone with no ties to the developer.
Ask in writing for an explanation and a revised timetable. Check with your lawyer what the contract says about delay before you withhold a payment. Our guide to construction delays sets out the next steps.
Store reports, photos, payment receipts and emails with their dates in one place. In a dispute, what counts is what you can prove.
Tools
The developer's photos alone are not enough. The larger the instalment, the more independent the evidence should be.
Regular and free, but selected by the developer. Check the date, your floor and shots of the whole building, not just flattering details.
A live walk-round with the site manager leaves less room for selection than photos. Ask to be shown specific places, such as your flat or the roof.
They show what may be built. Compare the number of floors and the floor area with the project, and ask for the approved amendment if anything differs.
It shows ownership of the land and any charges on it. A new entry during construction, such as a mortgage, is worth a question to the developer.
Inspects progress on site and spots defects that photos do not show. Ask for a written report with photographs.
A management company you plan to hire anyway can call in during construction. Agree in advance what it checks and what it does not.
The competent authorities check whether a building complies with its permit and with construction rules, and sign off the finished building. That oversight is about safety. It does not check whether the developer is keeping to your payment plan.
Frequently asked questions
Remote checks, stage payments, engineers, delay and access to the site.
From abroad you follow the build through dated photos and videos from the developer, video calls from the site and the permit documents. Before major instalments, have an independent engineer check progress on site.
Yes, if the developer agrees. Set out a visible construction stage for each instalment in the contract. Not every developer offers this, so ask before you reserve.
A structural engineer or surveyor with no link to the developer, often found through your lawyer or a local property manager. Ask for their qualifications and a written report.
Ask the developer in writing, collect evidence and check with a lawyer what the contract provides for delay. Do not withhold payments without legal advice, or you may end up in breach yourself.
Your contract decides. Agree a right of inspection for yourself or someone you appoint, by appointment and with safety equipment.
Last reviewed on 2 November 2026. Sources: Civil Code of Georgia (matsne.gov.ge): contracts of sale and contracts for work, Government Resolution No. 255 of 31 May 2019 on issuing building permits and commissioning buildings (matsne.gov.ge), National Agency of Public Registry (napr.gov.ge): registry extracts. This guide is not legal or tax advice.
Read next
How payment plans are structured, what to do about delays and who looks after the flat on the ground.
The more precisely stages, reports and access are agreed, the easier it is to follow the build from home.